PROJECT NAME
& LOCATION |
DESCRIPTION
/ SCOPE OF WORK |
DATE OF CONTRACT |
COMPLETION
DATE |
CONTRACTOR'S
ROLE |
|
ASEANA Power
Station Bldg.
ABP, Paranaque City |
Construction of 3-Storey
Commercial Building |
Feb. 2005 |
Feb. 2007 |
Prime Contractor |
Aseana Central
Lot 9
Roads and Drainage System
ABP, Paranaque City
|
Construction of Roads
and Drainage System |
June 2006 |
Dec. 2006 |
Prime Contractor |
|
Neo-Chinatown
Roads and Drainage System
ABP, Paranaque City |
Construction of Roads
and Drainage System |
Mar. 2006 |
Nov. 2006 |
Prime Contractor |
Central Boulevard
Road Project
(Diosdado Macapagal Blvd.)
ABP, Paranaque City |
Construction of 1200 l.m.
x 46 m Road, drainage system, streetlight
and landscaping |
Mar. 2002 |
Nov. 2003 |
Prime Contractor |
|
Rock Slope Type
Containment Wall
(1,500 L.M.) along
Roxas West Canal
ABP, Paranaque City |
Construction of Rock Slope
Type, containment wall (1,500 l.m.) along
Roxas West Canal |
Jun. 2001 |
Sep. 2002 |
Prime Contractor |
Roxas Canal West
Bridge
(Doña Eva Macapagal Bridge)
Pres. Diosdado
Macapagal Ave.
ABP, Paranaque City |
Design & Construction
of Two (2) Bridges 57.50 x 17.75 m |
Dec. 2001 |
Aug. 2002 |
Prime Contractor |
|
Pasig River
Rehabilitation Project
Package 4, Revetment
Makati City
|
Construction of 380 l.m.
revetment |
Mar. 2000 |
Feb. 2002 |
Prime Contractor |
Repair and Rehabilitation
of Lucena Multi-Purpose
Fish Port
Lucena City |
Demolition of Existing
Pier, construction of new deck and pile driving |
Dec. 1998 |
May 2000 |
Prime Contractor |
|
Ciudad Nuevo Project
Cavite City |
Dredging and Reclamation
(18.82 has.) |
Sep. 1989 |
Feb. 2000 |
Member of Joint Venture |
Philippine Ecopanel
Plant
Trece Martires, Cavite City |
Construction of Industrial
Plant and site development |
Mar. 1998 |
Oct. 1999 |
Prime Contractor |
|
Alabang-Zapote
Flyover Project
bet. Alabang & Zapote |
Flyover/Bridge Construction
and roadworks |
Mar. 1996 |
May. 1999 |
Member of Joint Venture |
Inland Channel
Reclamation |
Reclamation of Inland
Channel
|
Jun. 1986 |
Jan. 1988 |
Prime Contractor |
|
San Lorenzo South
Phase 1-C
(Subdivision Poject) |
Land Dev't. of 11.78 has
of land at Sta. Rosa Laguna involving drainage
and sewerage waterline, roadworks, open canal,
reinforced concrete box culvert concrte pavement,
cyclone wire, fencing, rubble masonry among
others. |
Jun. 1993 |
Feb. 1994 |
Prime Contractor |
66-B Canadcan
Alimanguan Road
Palawan
(ADB Assisted) |
Construction of 13 kms.
Class C Road locatde in the province of palawan
one (1) RCDG Bridge constructed third project
manemy, Alimanguan Bridge with net length
of 23.04 l.m. (1-span) and also construction
of eight (8) units barrel 1-3 barrel RCBC |
May 1988 |
Sept. 1990 |
Prime Contractor |
|
66-C Canadcan
Alimanguan Road
Palawan
(ADB Assisted) |
Construction of 15 Kms.
Class C Road, A;limaguan-Kemdeng Road Project
located in the Province of Palawan. Two (2)
RCDG Bridges constructed to this project namely:
New Agutaya Bridge and Kemdeng Bridge with
a net length of 43.88 l.m. (3-span) and 17.04
l.m. (1-span) respectively also construction
of 1-unit three barrel RCBC with a net length
of 11.70 l.m. |
May 1988 |
Dec. 1990 |
Prime Contractor |
Pangasinan -
Nueva Vizcaya
Road
CP - R1Y2C10 |
Construction of three
(3) units 1-2 barrels RCBC and widening construction
of its road approaches of 3 bridge namely,
Iris Bridge, Bitong Bridge and Dr. Acosta
Bridge |
May 1988 |
Dec. 1989 |
Prime Contractor |
|
Port of Zamboanga
Zamboanga City |
Dredging and Reclamation
Quay Structure Extension Const. of Ferry Pier
& Access Road |
July 1981 |
Mar. 1986 |
Member of Joint Venture |
Third IBD Highway
Project
Contract Package
'Z'-7 bridges
Passi - Dao - Sigma Road |
Construction of Seven
(7) Bridges |
1984 |
Feb. 1986 |
Member of Joint Venture |
|
Jaro - Iloilo
Divesion Road
Iloilo City |
Construction of Seven
(7) Bridges |
1982 |
Feb. 1983 |
Member of Joint Venture |
Pamantasan ng
Lungsod ng Maynila - College of Law,
Nursing and Library
Intramuros, Manila |
Project Management |
Mar. 31, 1995 |
Mar. 31, 1996 |
Project Manager |
|
R-1 Toll Expressway
Project -
KM 10 + 050 - 16 + 900
|
Provision of Toll Operation
Facilities and Improvement of Main Expressway
Including Extra Works. |
|
Oct. 1995 |
|
Tagaytay Road
Project Tagaytay City |
Road Construction
|
Dec. 1, 1991 |
Feb. 1993 |
Prime Contractor
|
|
Batangas Project
Batangas City |
Pile Driving |
|
Dec. 1992 |
Contractor |
Batangas Project
Batangas City
|
Dredging and Reclamation |
|
July. 1992 |
Contractor |
|
Tutuban Project
Tutuban |
Pile Driving |
|
Jul-92 |
Contractor |
Tutuban Project
Tutuban |
Pile Driving |
|
May-92 |
Contractor |
|
San Manuel Control
House |
Building Construction |
Nov. 5, 1990 |
Oct. 14, 1992 |
Prime Contractor |
PAG-ASA Project
(FFWS)
Bicol / Central Luzon |
Structures |
30-Apr-91 |
Feb. 23, 1990 |
Contractor |
|
Contract Package
R1Y2C10 |
Construction of Pangasinan-Nueva
Ecija Road. The Project consist of Construction
of three (3) units 1-2 barrel RCBC and Widening
Construction of its road approaches of 3 bridges
namely: Iris Bridge, Bitong Bridge and Dr.
Acosta Bridge with a net length of 9.00 m.,
14.00., and 27 m. respectively. |
May 18, 1988 |
Jan. 25, 1990 |
Prime Contractor |
Batangas Coal
Fired Thermal Power Plant (BCFTPP)
Calaca Batangas |
Dredging of Harbor and
Intake Beds of Batangas Coal Fired Thermal
Power Plant |
Dec. 2, 1988 |
Apr-89 |
Prime Contractor |
|
Five (5) NAtional
Electrification Administration Substation
|
Electrical installation,
local transports and construction of related
civil work for 5-NEA substation
a. 69 / 34.50
Kv Substation - Kagdianao
b. 69 / 13.20 Kv Substation - Iloilo
c. 34.50 / 13.20 kv Substation - Dapa
d. 69 / 13.20 Kv Substation - Balingoan
e. 1.3.20 Kv Substation - Davao |
|
Mar. 1987 |
Dec. 1988 |
Prime Contractor |
Site Grading Work Navotas Fishport Complex
(NFPC)
|
Salvaging of sunken vessel,
10 units, dredging and filling, 100,000 cu.m.
of unsuitable materials to be removed and
about 150,000 cu.m. of fill materials obtained
from dredging will be used to fill the areas,
general cleaning and grading. |
|
Dec. 8, 1986 |
Prime Contractor |
|
Lunzuran Heights
Subdivision
Zamboanga City
|
Land development which
includes drainage system, power distribution
system, road works, potable water distribution
system, 450 unit or mixed dwelling. |
|
|
|
Water Main Construction
Manggahan, Pasig, M.M. |
Excavtion, pipe laying,
surface restoration and pipe testing for the
proposed 225 l.m. of 50mm dia., 145 l.m. of
75 mm dia., 561 l.m. of 100 mm. dia. And 418
l.m. of 150 mm. dia of uPVC. |
|
Nov. 15, 1986 |
Prime Contractor |
|
Trenching on-shore
and off-shore for Cable Laying in the Island
of Guimaras, Surigao, Siargao, Camiguin and
Samal |
Coral Normal Soil Normal
Soil
Trenching Trenching Trenching Trenching
off-shore off-shore off-shore off-shore
1. Dapa - East Bucas island 1,050 5 - -
2. Kagdianao - Bucas 625 5 - 10
3. Camiguin Island 315 18 - 15
4. Iloilo - Guimaras Island 222 21 535 30
5. Davoa - Samal - 25 500 - |
|
June-86 |
Prime Contractor |
PNB Congenerics
Building (Foundation Works)
Phase I
Reclamation Area, Roxas Blvd., Pasay City,
Metro Manila |
1. Piling Work - 811 Pile
Positions - Driving 18" dai. TSP
2. Concrete Works
a. 4,000 psi concrete - 4,240 cu.m.
b. 2,000 psi concrte - 156 cu.m.
3. reinforcing Bar Work - 1,000 tons
4. Steel Works (piling Tip, ring band) |
|
June-86 |
Contractor |
|
Philippines National
Bank, Iloilo Branch |
Pile Driving |
1981 |
1981 |
Contractor |
Quad 2 Commercial
Complex |
Pile Driving |
1980 |
1980 |
Contractor |
|
Frabal Commercial
and Industrial Complex |
Supply, Deliver and
Diving of Piles |
1979 |
1979 |
Contractor |
Marikina Bridge
Diversion Road Project Phase I, Section I |
3,151 m. long, 4 Lanes,
2 Span of 22.50 m., 9 Spans of 30.00 m. width
24 units of 22.50 m. and 108 units of 20.00
m. AASHTO Girder, E. C. piers and slab, 6,116
m. of PSC piles |
1979 |
1979 |
Contractor |
|
Tawi-Tawi Provincial
Capitol Building
Phase II-A |
|
1979 |
1979 |
Contractor |
Tawi-Tawi Provincial
Capitol Building |
Phase I & II Two (2)
storey U-shape reinforced concrete structure
with a basement floor on the left wing with
a total floor area of 2,245 sq.m. more or
less, a deck roof with a 100 m. dia. Session
hall with a total floor area of 945 sq.m.
more or less |
1977 |
1977 |
Contractor |
|
Hotel Zambayan
Executive Club Building |
Part two (2) storey reinfrced
concrete structure with total floor area of
1,380 sq.m. more or less and completed with
various sports |
1978 |
1978 |
Contractor |
Hotel Zambayan
Complex 75-Room Hotel Building |
Three (3) Storey reinforced
concrete structure with deck roof complete
with furnishing and equipment with a total
floor area of 5,344 sq.m. more or less |
1977 |
1977 |
Contractor |
|
Philippines Veterans Bank,
Zamboanga Branch Building
|
Two (2) storey reinforced
concrete structure with mezzanine at the ground
floor bank vault and security system with
a total floor area of 800 sq.m. or more or
less including site development work, landscapping
and underground water tank. |
1978 |
1978 |
Contractor |
New PLDT Zamboanga
Exchange Bldg., I Commercial Bldg.
ME-EE Room |
Part two (2) storey reinforced
concrete structure with deck roof cable vault
with a total floor area of 827 sq.m. more
or less - - - Fence concrete driveway and
underground water storage tank. |
1977 |
1977 |
Contractor |
|
PHHC Bridge |
Three (3) Spans bridge
containing two (2) 15.00 m. pre-stressed concrete
girder and spans and one (1) 80 ft. pre-stressed
concrte girder center span with reinforced
concrete abutment and pier resting on pre-stressed
concrete deck slab and railing. |
1977 |
1977 |
Contractor |
Limurain Bridge
No. Km. 162.70 |
One (1) Span 22.00 m.
RCDG Bridge with reinforced concrete abutment,
concrete deck spab and railing.
|
1976 |
1976 |
Contractor |
|
Barter Trade Market
Building |
Two (2) Storey semi-concrete
commercial building with reinforced columns
and beam wooden sidings and flooring, gangnail
trusses and G.I. Sheets roofing complete with
wooden market stalls. |
1976 |
1976 |
Contractor |
Laguna Estate
Development Corporation (Camp Facilities) |
One (1) Storey Building
with reinforced Concrete columns and beams.
CHB walls, concrte slab, gangnail trusses
and structural steel trusses with G.I. sheet
roofing. |
1975 |
1975 |
Contractor |
|
LEDC Office |
a. Canteen Bldg.--- 120
sq.m.
b. BunkHouse ----- 180 sq.m.
c. Motor Pool ------ 300 sq.m. |
1975 |
1975 |
Contractor |
LEDC Bridge
(Canlubang) |
One (1) Span 7.00 m.
concrete Bridge with reinforced concrte abutment
pre-stressed u-beams deck slab and concrete
railings. |
1975 |
1975 |
Contractor |
|
Sto. Nino Rairoad
Overpass Bridge
No. Km. 69+406 |
Along Olongapo-Gapan Road,
One (1) Span of 23.20 m. with reinforced concrete
AASHTO girders, concrete deck slab galvanized
steel. |
1975 |
1975 |
Contractor |
| Administration
Building |
Two (2) Storey with pre-stresed
concrete columns, beams and tee-joint with
total floor area of 380 sq.m. |
1974 |
1974 |
Contractor |
|
Canteen Building |
One (1) Storey with reinforced
concrete with kitchen and self-service counters
and a floor area of 423 sq.m. |
1974 |
1974 |
Contractor |
TPA Warehouse |
One (1) Storey with pre-stressed
concrete columns, beams and structural steel
roof trusses with a floor area of 900 sq.,m.
|
1974 |
1974 |
Contractor |
|
Ethylene Glycol
Recovery Building |
Reinforced Concrete columns,
beams and slab, 4-storey with a total floor
area of 640 sq.m. |
1974 |
1974 |
Contractor |
Utilities Building |
R.C. Colums and beams
sed concrete columns, beams and structural
steel roof trusses with a floor artea of 900
sq.m. |
1974 |
1974 |
Contractor |
|
Ubihan Bridge |
Four (4) Span of about
19.60 m. each with prestressed concrete piles
encased with steel monotubes. R.C. abutment
and piers, prestressed concrete girder, concrete
slab and railings.
|
1974 |
1974 |
Contractor |
Taliptip Bridge |
Four (4) Span of about
27.55 m. each with prestressed concrete piles
R.C. abutment and piers, prestressed concrete,
concrete slab and railings. |
1974 |
1974 |
Contractor |
|
Vinyl Plant Extension |
31.60 m,. Structural streel
trusses on concrete columns G.I. roofing CHB
walls. |
1973 |
1973 |
Contractor |
ACB Warehouse |
33.00 m. x 60.00 m. width
structural steel columns abd trusses and G.I.
roofing. CHB walls and 100 sq.m. of parking
areas. |
1973 |
1973 |
Contractor |
|
Activated Carbon
Plant Access Road |
9.60 m. wide, 350 m. long
with average escombro fill of 0.60 m. and
selected borrow surfacing |
1973 |
1973 |
Contractor |
B. F. Homes
Phase III Bridge |
One (1) Span of 10.00
m. lonf with prestressed concrete deck on
concrete pile beams |
1973 |
1973 |
Contractor |
|
Ramitex Waving
Mill Building |
With floor area of 11.360
sq.m. with structural steel roof frames R.
C. Columns and beams asbestos roofing and
CHB walls. |
1973 |
1973 |
Contractor |
100,000 Gallons
Ground R.C. Reservoir |
With Floor area of 1,400
sq.m. with wood roof frames. R.C. columns
asphalt flooring and G.I. roofing. |
1972 |
1972 |
Contractor |
|
Sea Front Subdivision
Phase I |
363 m. of aspahlt with
curb and gutter and underground drainage system. |
1971 |
1971 |
Contractor |
Boiler House Building |
R. C. columns and beams
structural steel frame with asbestos roofing
including installation of firebricks and boiler. |
1969 |
1969 |
Contractor |
|
Porous
Concrete Plant |
Floor area of 13.00 sq.m.
structural steel columns and trusses with
asbestos sidings and roofing including the
construction of machinery foundations and
the installation of machineries |
1969 |
1969 |
Contractor |
Plant Building
Extension and Machinery Foundations |
R. C. roofing for plant
building extension and machinery foundation
for continous galvanizing plant. Administration
nuilding of CHB, driveways, parking areas,
drainage system, fence and entrance gate. |
1968 |
1968 |
Contractor |
|
Cement Plant Extension
4th Unit |
a. Packhouse Extension
b. Crusher Building
c. Raw Mill Bins
d. Screen House
e. Renovation of Plant Office
f. Packhouse Concrete Pavement
g. Materials Storage Shed Extension |
1967 |
1967 |
Contractor |
Pharmaceutical Manufacturing and Office Building
|
1,000 sq.m. of warehouse
and plant area, 1,000 sq.m. of office area,
concrete columns and beams with structural
steel roof frames and aluminum sidings for
plant area. Prestressed concrete floor system
for office area, driveways perimeter fence,
fire pond, excluding electrical perimeter
and air-conditioning. |
1966 |
1966 |
Contractor |
|
Service Part and Office Building
|
1,500 sq.m. of warehouse
area 500 sq.m. of office area with R. C. columns
and beams and structural steel roof frames
and aluminum roofing for warehouse area prestressed
T-joist roof perimeter fence, driveways, electrical
and air-conditioning |
1966 |
1966 |
Contractor |
Plant Extension |
a. Calcinator
b. Burning Flatform
c. Smoke Stack |
|
|
Contractor |
|
Plant
Extension |
Additional Electric Precipitator |
1964 |
1964 |
Contractor |
Development of
Sta. Maria Villa Subdivision |
Area - 11 Hectares, Road
length - 2.0 kms. |
1964 |
1964 |
Contractor |
|
Plant Extension |
Warehouse with structural
steel trusses, concrte columns, CHB wall asbestos,
roofing 90' x 100' |
1964 |
1964 |
Contractor |
Development of
Malinta Village Subdivision |
12 kms., 3.2 kms. Of road
a. Road Grading
b. Construction of Curbs and Gutter
c. Drainage System
d. Asphalting |
1961 |
1961 |
Contractor |
|
R. C. Wharf Extension |
P. C. Sheet piles with
Class III rock fill |
1961 |
1961 |
Contractor |
Construction
of Carbon Container Factory |
Structural Steel trusses
and columns, CHB sidings and G. E. roofing |
1961 |
1961 |
Contractor |
|
Two (2) Unit Warehouse |
With structural steel
frame asvestos, siding and roofing 66' x 169' |
1961 |
1961 |
Contractor |
Plant Extension |
Kline Foundation |
1960 |
1960 |
Contractor |
|
Cement
Bag Factory |
120 ' x 120 with structural
steel trusses concrete columns, CHB walls,
site grading construction of road drainage
system. |
1960 |
1960 |
Contractor |
Terminal Facilities |
a. Site grading
b. Tanks Foundation
c. Perimeter fence
d. Electrical Control Building
f. Laboratory Building |
1960 |
1960 |
Contractor |